54-460550 / Buena Vista Avenue and Cactus Drive - On August 30th NPL is scheduled to work on Buena Vista Avenue starting from Cactus Drive continuing east to Palm Drive. Gas main is planned to be installed on the north side of Buena Vista Avenue. Permit number SUB-21-90.
54-459996 / Estrella Avenue and Palm Drive - On August 30th NPL is scheduled to work on Estrella Avenue starting from Cactus Drive continuing east to Palm Drive. Gas main is planned to be installed on the south side of Estrella Avenue. Permit number SUB-21-91.
54-459116 / Cahuilla Avenue and Via Real - On August 30th NPL is scheduled to work on Cahuilla Avenue starting from Via Real continuing east to Cactus Drive. Gas main is planned to be installed on the north side of Cahuilla Avenue. Permit number SUB-21-87.
54-463139 / 3rd Street and Cactus Drive - On August 30th NPL is scheduled to work on 3rd Street starting from Cactus Drive continuing east to Palm Drive. Gas main is planned to be installed on the north side of 3rd Street. Permit number SUB-21-86.
54-463137 / Buena Vista Avenue and Palm Drive - On September 7th NPL is scheduled to work on Buena Vista Avenue starting from Palm Drive continuing east to Verbena Drive. Gas main is planned to be installed on the south side of Buena Vista Avenue. Permit number SUB-21-83.
54-459118 / Desert View Avenue and Cactus Drive - On September 7th NPL is scheduled to work on Desert View Avenue starting from Cholla Drive continuing east to Cactus Drive. Gas main is planned to be installed on the north side of Desert View Avenue. Permit number SUB-21-88.
54-463132 / 2nd Street and Cactus Drive - On September 7th NPL is scheduled to work on 2nd Street starting from Cactus Drive continuing east to Palm Drive. Gas main is planned to be installed on the north side of 2nd Street. Permit number SUB-21-82.
Dispatch Center Tenant Improvement Project Update
The demolition phase of this project has been completed and the installation of plumbing has begun. The new Dispatch Center will have a breakroom, two restrooms/locker rooms, showers, and a janitorial closet. These additions require brand new plumbing installation. The project management company, CLM Consultants, is making sure this highly anticipated project is completed correctly and on time.
Dispatch Center Tenant Improvement Project
The first step to bringing emergency dispatch services back to Desert Hot Springs has started. Diamond Construction, Inc. has begun the tenant improvements needed to house the new high-tech Dispatch Center. This project is just one of the many upcoming capital improvement projects demonstrating the City's dedication to improving public safety.